Start with the loads and the required outcome

Generator selection should begin with the facility's operating requirement: which loads must remain available, how quickly supply must be restored and what happens if the standby system does not operate. The largest available generator is not automatically the best selection.

The assessment should distinguish running load from starting demand. Motors, compressors, pumps, lifts and transformers can impose short-duration demands that affect voltage and frequency recovery. Electronic loads may introduce harmonics, while altitude, ambient temperature and future expansion can change the usable rating.

  • Essential and non-essential load schedules
  • Largest motor or compressor starting method
  • Expected operating sequence and load steps
  • Power factor, harmonic loads and future capacity
  • Site altitude, temperature and generator derating

Confirm the site, fuel and mechanical requirements

The installation location must support safe access, maintenance and reliable operation. A generator needs a suitable base, weather protection where required, adequate combustion and cooling airflow, and an exhaust route that does not expose people or occupied spaces to fumes.

Fuel storage and pipework should suit the expected runtime and applicable fire, environmental and site requirements. Noise, vibration, drainage, lifting access and the route for bringing the set onto site are practical design issues that should be resolved before delivery.

  • Equipment access, lifting route and service clearances
  • Cooling-air inlet and hot-air discharge separation
  • Exhaust routing, insulation and safe termination
  • Fuel capacity, containment and refilling access
  • Base, vibration isolation, noise and drainage

Design the electrical connection as a complete system

Cable sizing depends on generator rating, route length, installation method, ambient conditions, grouping and acceptable voltage drop. The design must also confirm fault protection, isolation, phase sequence, labelling and the relationship between generator protection and downstream distribution.

Earthing and neutral arrangements require particular care because the correct approach depends on the supply architecture and switching arrangement. The neutral must not be assumed to be permanently common or automatically switched; the design should establish how the installation behaves on utility and generator supply and prevent unintended parallel paths.

  • Generator breaker rating and discrimination with downstream protection
  • Cable current capacity, voltage drop and short-circuit withstand
  • Earthing, bonding and neutral-switching philosophy
  • Phase rotation, metering and surge-protection interfaces
  • Safe isolation and clearly identified emergency controls

Specify the ATS and changeover sequence

An automatic transfer switch is part of the control and protection system, not only a switching device. Its rating, withstand capability, pole configuration and mechanical or electrical interlocking must suit the installation. Utility and generator sources must not be connected together unless a purpose-designed synchronising system has been engineered for parallel operation.

The sequence should define how utility failure is detected, when the start signal is issued, how long the generator warms up, when the load transfers and how the system returns after stable utility power is restored. Delay settings should prevent unnecessary starts or rapid switching during short disturbances.

  • Utility voltage and frequency sensing
  • Start delay, warm-up and transfer timing
  • Source interlocking and position feedback
  • Return-to-utility delay and generator cool-down
  • Manual operation and safe maintenance bypass requirements

Configure the generator controller or PLC around real failure modes

Controller settings should match the engine, alternator, protection devices and intended operating sequence. Inputs and outputs need to be verified at the terminals, not accepted from labels alone. Where a PLC, building-management system or SCADA platform is involved, the signal list should distinguish commands, permissives, status indications and alarms.

Useful remote visibility normally includes availability, running state, source position, common alarm, low fuel and key shutdown conditions. Remote start commands require controlled permissions and interlocks so that maintenance personnel are not exposed to an unexpected start.

  • Start, stop and emergency-stop circuits
  • Oil pressure, coolant temperature, speed and electrical protection
  • Breaker and ATS position feedback
  • Alarm history, communications and remote notifications
  • Maintenance mode and unexpected-start prevention

Commission the system under controlled conditions

A no-load start confirms only part of the installation. Commissioning should verify the complete sequence under an agreed test plan: utility failure, engine start, voltage and frequency stabilisation, transfer, load acceptance, utility return and cool-down. Critical facilities need a coordinated shutdown and contingency plan before live transfer testing.

Readings should be recorded by phase, including voltage, current, frequency and load balance. The team should also observe temperatures, leaks, smoke, vibration, alarms and the response to load steps. Where the facility cannot provide enough load for a meaningful test, an appropriately planned load-bank test may be required.

  • Insulation, continuity, earthing and phase-sequence checks
  • Protection, alarm and emergency-stop verification
  • Automatic failure and restoration sequence
  • Loaded voltage, frequency, current and phase balance
  • Fuel, cooling, exhaust and abnormal-condition observations

Handover, workmanship warranty and continued maintenance

The client should receive operating instructions, controller information, test records, equipment documentation and a clear explanation of normal, manual and emergency operation. Circuit labels and drawings should match the installed system so that future fault-finding does not begin with guesswork.

A workmanship warranty should state its duration, the installation work it covers, exclusions and the process for reporting a defect. It is separate from the generator manufacturer's equipment warranty. Continued reliability also depends on scheduled servicing, battery checks, fuel management and periodic automatic changeover tests under safe operating conditions.

  • Approved drawings, cable schedules and settings records
  • Commissioning results and outstanding-action list
  • Operator training and emergency contact process
  • Defined workmanship and equipment-warranty responsibilities
  • Maintenance intervals, exercise plan and service log

What to send when requesting a generator installation quotation

A better initial brief produces a more useful proposal. Include the Cape Town or Western Cape site location, recent electricity data, photographs of the main distribution boards, a list of essential loads, available drawings, the required backup duration and any existing generator, solar or UPS equipment.

AfriTech can then assess whether the next step should be a site survey, load study, generator and ATS specification, or a complete supply-and-installation scope. The quotation should make the design assumptions and exclusions visible before equipment is ordered.